— Project Summary

Queue ID
PJM-AH2-338
Capacity
160 MW
Technology
Solar
Status
active
Location
Winnebago, IL
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL + Live

160 MW generation in Winnebago, IL · In queue since March 2022 · Proposed COD July 2027

160 MW

Capacity

1

Components

Solar

4 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

5y 4m

In Study38%
Queue EntryMar 10, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-07-30

Project Details

State

IL

County

Winnebago

Region

PJM

Developer

Utility

ComEd

Entity

PJM

Point of Interconnection

Wempletown 138 kV

Data Source

LBNL + Live

No news available for this project.