— Project Summary

Queue ID
PJM-AH2-295
Capacity
40 MW
Technology
Solar
Status
active
Location
Greene, PA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL + Live

40 MW generation in Greene, PA · In queue since March 2022 · Proposed COD September 2025

40 MW

Capacity

1

Components

Solar

4 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 6m

Schedule

6 months past proposed COD

In Study38%
Queue EntryMar 10, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-09-15

Project Details

State

PA

County

Greene

Region

PJM

Developer

Utility

APS

Entity

PJM

Point of Interconnection

Emerald 25 kV

Data Source

LBNL + Live

No news available for this project.