BetaActiveBatteryPJMLBNL + Live
82.4 MW storage in Henry, OH · In queue since March 2022 · Proposed COD December 2024
82.4 MW
Capacity
1
Components
Battery
4 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 9m
Schedule
16 months past proposed COD
In Study38%
Queue EntryMar 10, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-12-01
Project Details
State
OH
County
Henry
Region
PJM
Developer
—
Utility
AMPT
Entity
PJM
Point of Interconnection
Napoleon Muni 138 kV
Data Source
LBNL + Live
No news available for this project.