— Project Summary

Queue ID
PJM-AH2-267
Capacity
100 MW
Technology
Solar+Battery
Status
active
Location
Clearfield, PA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryPJMLBNL + Live

100 MW hybrid in Clearfield, PA · In queue since March 2022 · Proposed COD July 2025

100 MW

Capacity

1

Components

Solar

4 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 4m

Schedule

9 months past proposed COD

In Study38%
Queue EntryMar 9, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-07-01

Project Details

State

PA

County

Clearfield

Region

PJM

Developer

Utility

PENELEC

Entity

PJM

Point of Interconnection

Modera - BioEnergy Tap 115 kV

Data Source

LBNL + Live

No news available for this project.