100 MW hybrid in Clearfield, PA · In queue since March 2022 · Proposed COD July 2025
100 MW
Capacity
1
Components
Solar
4 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 4m
Schedule
9 months past proposed COD
In Study38%
Queue EntryMar 9, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-07-01
Project Details
State
PA
County
Clearfield
Region
PJM
Developer
—
Utility
PENELEC
Entity
PJM
Point of Interconnection
Modera - BioEnergy Tap 115 kV
Data Source
LBNL + Live
No news available for this project.