— Project Summary

Queue ID
PJM-AH2-266
Capacity
25 MW
Technology
Solar
Status
active
Location
Charles, MD
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL + Live

25 MW generation in Charles, MD · In queue since March 2022 · Proposed COD March 2026

25 MW

Capacity

1

Components

Solar

4 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4 years

Schedule

1 months past proposed COD

In Study38%
Queue EntryMar 10, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-03-01

Project Details

State

MD

County

Charles

Region

PJM

Developer

Utility

SMECO

Entity

PJM

Point of Interconnection

Hughesville-Cedarville 69kV

Data Source

LBNL + Live

No news available for this project.