— Project Summary

Queue ID
PJM-AH2-257
Capacity
400 MW
Technology
Solar
Status
active
Location
Vermillion, IN
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL + Live

400 MW generation in Vermillion, IN · In queue since March 2022 · Proposed COD September 2024

400 MW

Capacity

1

Components

Solar

4 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

2y 6m

Schedule

18 months past proposed COD

In Study38%
Queue EntryMar 9, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-09-29

Project Details

State

IN

County

Vermillion

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Dequine - Eugene 345 kV

Data Source

LBNL + Live

No news available for this project.