BetaActiveWindPJMLBNL + Live
83.259 MW generation in Cambria, PA · In queue since March 2022 · Proposed COD December 2028
83.259 MW
Capacity
1
Components
Wind
4 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
6y 9m
In Study38%
Queue EntryMar 9, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-31
Project Details
State
PA
County
Cambria
Region
PJM
Developer
—
Utility
PENELEC
Entity
PJM
Point of Interconnection
Carrolltown 46 kV
Data Source
LBNL + Live
No news available for this project.