— Project Summary

Queue ID
PJM-AH2-239
Capacity
49 MW
Technology
Solar+Battery
Status
active
Location
Trumbull, OH
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryPJMLBNL + Live

49 MW hybrid in Trumbull, OH · In queue since March 2022 · Proposed COD March 2027

49 MW

Capacity

1

Components

Solar

4 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

5 years

In Study38%
Queue EntryMar 10, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-03-07

Project Details

State

OH

County

Trumbull

Region

PJM

Developer

Utility

ATSI

Entity

PJM

Point of Interconnection

Trumbull138 kV

Data Source

LBNL + Live

No news available for this project.