BetaActiveSolarPJMLBNL + Live
74.715 MW generation in Wicomico, MD · In queue since March 2022 · Proposed COD June 2026
74.715 MW
Capacity
1
Components
Solar
4 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
4y 3m
In Study38%
Queue EntryMar 8, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-06-30
Project Details
State
MD
County
Wicomico
Region
PJM
Developer
—
Utility
DPL
Entity
PJM
Point of Interconnection
Mt. Hermon 69 kV
Data Source
LBNL + Live