BetaActiveSolarPJMLBNL + Live
85 MW generation in Crawford, OH · In queue since March 2022 · Proposed COD January 2026
85 MW
Capacity
1
Components
Solar
4 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 10m
Schedule
3 months past proposed COD
In Study38%
Queue EntryMar 4, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-01-01
Project Details
State
OH
County
Crawford
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Chatfield 69 kV
Data Source
LBNL + Live
No news available for this project.