BetaActiveSolarPJMLBNL + Live
19.8 MW generation in Armstrong, PA · In queue since March 2022 · Proposed COD March 2026
19.8 MW
Capacity
1
Components
Solar
4 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
4 years
Schedule
1 months past proposed COD
In Study38%
Queue EntryMar 4, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-03-01
Project Details
State
PA
County
Armstrong
Region
PJM
Developer
—
Utility
APS
Entity
PJM
Point of Interconnection
Kittanning - Rural Valley 25 kV
Data Source
LBNL + Live
No news available for this project.