— Project Summary

Queue ID
PJM-AH2-163
Capacity
19.8 MW
Technology
Solar
Status
active
Location
Armstrong, PA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL + Live

19.8 MW generation in Armstrong, PA · In queue since March 2022 · Proposed COD March 2026

19.8 MW

Capacity

1

Components

Solar

4 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4 years

Schedule

1 months past proposed COD

In Study38%
Queue EntryMar 4, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-03-01

Project Details

State

PA

County

Armstrong

Region

PJM

Developer

Utility

APS

Entity

PJM

Point of Interconnection

Kittanning - Rural Valley 25 kV

Data Source

LBNL + Live

No news available for this project.