— Project Summary

Queue ID
PJM-AH2-146
Capacity
87.2 MW
Technology
Solar+Battery
Status
active
Location
Adams, OH
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryPJMLBNL + Live

87.2 MW hybrid in Adams, OH · In queue since February 2022 · Proposed COD December 2027

87.2 MW

Capacity

1

Components

Solar

4y 1m

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

5y 10m

In Study38%
Queue EntryFeb 28, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-30

Project Details

State

OH

County

Adams

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Adams - Seaman 69 kV

Data Source

LBNL + Live

No news available for this project.