BetaActiveSolarBatteryPJMLBNL + Live
87.2 MW hybrid in Adams, OH · In queue since February 2022 · Proposed COD December 2027
87.2 MW
Capacity
1
Components
Solar
4y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5y 10m
In Study38%
Queue EntryFeb 28, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-30
Project Details
State
OH
County
Adams
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Adams - Seaman 69 kV
Data Source
LBNL + Live
No news available for this project.