— Project Summary

Queue ID
PJM-AH2-144
Capacity
150 MW
Technology
Battery
Status
active
Location
King George, VA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryPJMLBNL + Live

150 MW storage in King George, VA · In queue since February 2022 · Proposed COD June 2027

150 MW

Capacity

1

Components

Battery

4y 1m

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

5y 4m

In Study38%
Queue EntryFeb 28, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-06-01

Project Details

State

VA

County

King George

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Birchwood-NUG 230kV

Data Source

LBNL + Live

No news available for this project.