BetaActiveSolarPJMLBNL + Live
10 MW generation in Amherst, VA · In queue since February 2022 · Proposed COD December 2026
10 MW
Capacity
1
Components
Solar
4y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
4y 10m
In Study38%
Queue EntryFeb 28, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-01
Project Details
State
VA
County
Amherst
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Monroe - Coolwell 12.47 kV
Data Source
LBNL + Live
No news available for this project.