50 MW generation in Luzerne, PA · In queue since February 2022 · Proposed COD June 2025
50 MW
Capacity
1
Components
Solar
4y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 4m
Schedule
9 months past proposed COD
In Study38%
Queue EntryFeb 28, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-06-19
Project Details
State
PA
County
Luzerne
Region
PJM
Developer
—
Utility
PPL
Entity
PJM
Point of Interconnection
Harwood- McAdoo 69 kV
Data Source
LBNL + Live
No news available for this project.