BetaActiveBatteryPJMLBNL + Live
300 MW storage in City Of Chesapeake, VA · In queue since March 2022 · Proposed COD March 2027
300 MW
Capacity
1
Components
Battery
4 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5 years
In Study38%
Queue EntryMar 1, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-03-01
Project Details
State
VA
County
City Of Chesapeake
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Fentress- Landstown 230kV
Data Source
LBNL + Live
No news available for this project.