— Project Summary

Queue ID
PJM-AH2-133
Capacity
300 MW
Technology
Battery
Status
active
Location
City Of Chesapeake, VA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryPJMLBNL + Live

300 MW storage in City Of Chesapeake, VA · In queue since March 2022 · Proposed COD March 2027

300 MW

Capacity

1

Components

Battery

4 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

5 years

In Study38%
Queue EntryMar 1, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-03-01

Project Details

State

VA

County

City Of Chesapeake

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Fentress- Landstown 230kV

Data Source

LBNL + Live

No news available for this project.