18 MW storage in Burlington, NJ · In queue since February 2022 · Proposed COD September 2023
18 MW
Capacity
1
Components
Battery
4y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
1y 7m
Schedule
31 months past proposed COD
In Study38%
Queue EntryFeb 25, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-09-19
Project Details
State
NJ
County
Burlington
Region
PJM
Developer
—
Utility
PSEG
Entity
PJM
Point of Interconnection
Burlington 26 kV
Data Source
LBNL + Live
No news available for this project.