— Project Summary

Queue ID
PJM-AH2-126
Capacity
100 MW
Technology
Battery
Status
active
Location
Jefferson, OH
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryPJMLBNL + Live

100 MW storage in Jefferson, OH · In queue since February 2022 · Proposed COD October 2026

100 MW

Capacity

1

Components

Battery

4y 1m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4y 8m

In Study38%
Queue EntryFeb 25, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-10-31

Project Details

State

OH

County

Jefferson

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Tidd 138 kV

Data Source

LBNL + Live

No news available for this project.