BetaActiveBatteryPJMLBNL + Live
100 MW storage in KY · In queue since February 2022 · Proposed COD December 2028
100 MW
Capacity
1
Components
Battery
4y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
6y 10m
In Study38%
Queue EntryFeb 26, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-01
Project Details
State
KY
County
—
Region
PJM
Developer
—
Utility
ComEd
Entity
PJM
Point of Interconnection
Kensington 138 kV
Data Source
LBNL + Live
No news available for this project.