BetaActiveSolarPJMLBNL + Live
15 MW generation in Crawford, PA · In queue since February 2022 · Proposed COD December 2025
15 MW
Capacity
1
Components
Solar
4y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 10m
Schedule
3 months past proposed COD
In Study38%
Queue EntryFeb 25, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-30
Project Details
State
PA
County
Crawford
Region
PJM
Developer
—
Utility
PENELEC
Entity
PJM
Point of Interconnection
Morgan Street - Titusville 34.5 kV
Data Source
LBNL + Live
No news available for this project.