85 MW generation in Cambria, PA · In queue since February 2022 · Proposed COD January 2026
85 MW
Capacity
1
Components
Solar
4y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 11m
Schedule
3 months past proposed COD
In Study38%
Queue EntryFeb 23, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-01-01
Project Details
State
PA
County
Cambria
Region
PJM
Developer
—
Utility
PENELEC
Entity
PJM
Point of Interconnection
Garman - Westover South 115 kV
Data Source
LBNL + Live