BetaActiveSolarBatteryPJMLBNL + Live
250 MW hybrid in St. Joseph, IN · In queue since February 2022 · Proposed COD February 2026
250 MW
Capacity
1
Components
Solar
4y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
4 years
Schedule
1 months past proposed COD
In Study38%
Queue EntryFeb 22, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-02-27
Project Details
State
IN
County
St. Joseph
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Olive - Dumont 345 kV
Data Source
LBNL + Live
No news available for this project.