BetaActiveGasPJMLBNL + Live
20 MW generation in Monroe, OH · In queue since February 2022 · Proposed COD June 2022
20 MW
Capacity
1
Components
Gas
4y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
4 months
Schedule
46 months past proposed COD
In Study38%
Queue EntryFeb 19, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-06-30
Project Details
State
OH
County
Monroe
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Hannibal 138 kV
Data Source
LBNL + Live
No news available for this project.