— Project Summary

Queue ID
PJM-AH2-111
Capacity
20 MW
Technology
Gas
Status
active
Location
Monroe, OH
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveGasPJMLBNL + Live

20 MW generation in Monroe, OH · In queue since February 2022 · Proposed COD June 2022

20 MW

Capacity

1

Components

Gas

4y 1m

In Queue

In Progress (unknown study)

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

4 months

Schedule

46 months past proposed COD

In Study38%
Queue EntryFeb 19, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-06-30

Project Details

State

OH

County

Monroe

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Hannibal 138 kV

Data Source

LBNL + Live

No news available for this project.