BetaActiveSolarPJMLBNL + Live
19.5 MW generation in Dorchester, MD · In queue since February 2022 · Proposed COD May 2023
19.5 MW
Capacity
1
Components
Solar
4y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
1y 3m
Schedule
35 months past proposed COD
In Study38%
Queue EntryFeb 1, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-05-01
Project Details
State
MD
County
Dorchester
Region
PJM
Developer
—
Utility
DPL
Entity
PJM
Point of Interconnection
West Cambridge - Airey 69 kV
Data Source
LBNL + Live
No news available for this project.