BetaActiveSolarBatteryPJMLBNL + Live
32 MW hybrid in Greene, OH · In queue since January 2022 · Proposed COD December 2025
32 MW
Capacity
1
Components
Solar
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 11m
Schedule
3 months past proposed COD
In Study38%
Queue EntryJan 31, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-31
Project Details
State
OH
County
Greene
Region
PJM
Developer
—
Utility
Dayton
Entity
PJM
Point of Interconnection
Jasper 69 kV
Data Source
LBNL + Live
No news available for this project.