— Project Summary

Queue ID
PJM-AH2-082
Capacity
33.25 MW
Technology
Solar
Status
active
Location
Fayette, OH
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL + Live

33.25 MW generation in Fayette, OH · In queue since January 2022 · Proposed COD January 2025

33.25 MW

Capacity

1

Components

Solar

4y 2m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3 years

Schedule

15 months past proposed COD

In Study38%
Queue EntryJan 27, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-01-03

Project Details

State

OH

County

Fayette

Region

PJM

Developer

Utility

Dayton

Entity

PJM

Point of Interconnection

New Holland - Washington Courthouse 69 kV

Data Source

LBNL + Live

No news available for this project.