BetaActiveSolarPJMLBNL + Live
35.5 MW generation in Fayette, OH · In queue since January 2022 · Proposed COD September 2025
35.5 MW
Capacity
1
Components
Solar
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 8m
Schedule
6 months past proposed COD
In Study38%
Queue EntryJan 27, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-09-19
Project Details
State
OH
County
Fayette
Region
PJM
Developer
—
Utility
Dayton
Entity
PJM
Point of Interconnection
Bentley Farms 69 kV
Data Source
LBNL + Live
No news available for this project.