99.67 MW generation in Charlotte, VA · In queue since January 2022 · Proposed COD January 2025
99.67 MW
Capacity
1
Components
Solar
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3 years
Schedule
15 months past proposed COD
In Study38%
Queue EntryJan 27, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-01-03
Project Details
State
VA
County
Charlotte
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Dryburg - Chase City 230 kV
Data Source
LBNL + Live