BetaActiveBatteryPJMLBNL + Live
29.12 MW storage in City Of Hampton, VA · In queue since January 2022 · Proposed COD July 2024
29.12 MW
Capacity
1
Components
Battery
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 6m
Schedule
21 months past proposed COD
In Study38%
Queue EntryJan 21, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-07-01
Project Details
State
VA
County
City Of Hampton
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Hampton VA 2
Data Source
LBNL + Live
No news available for this project.