— Project Summary

Queue ID
PJM-AH2-072
Capacity
62.1 MW
Technology
Battery
Status
active
Location
Washington, VA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryPJMLBNL + Live

62.1 MW storage in Washington, VA · In queue since January 2022 · Proposed COD January 2025

62.1 MW

Capacity

1

Components

Battery

4y 2m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3 years

Schedule

15 months past proposed COD

In Study38%
Queue EntryJan 21, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-01-01

Project Details

State

VA

County

Washington

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Damascus 69 kV

Data Source

LBNL + Live