BetaActiveBatteryPJMLBNL + Live
62.1 MW storage in Washington, VA · In queue since January 2022 · Proposed COD January 2025
62.1 MW
Capacity
1
Components
Battery
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3 years
Schedule
15 months past proposed COD
In Study38%
Queue EntryJan 21, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-01-01
Project Details
State
VA
County
Washington
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Damascus 69 kV
Data Source
LBNL + Live
No news available for this project.