BetaActiveSolarPJMLBNL + Live
5 MW generation in Jefferson, PA · In queue since January 2022 · Proposed COD December 2023
5 MW
Capacity
1
Components
Solar
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
1y 11m
Schedule
28 months past proposed COD
In Study38%
Queue EntryJan 4, 2022
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-12-15
Project Details
State
PA
County
Jefferson
Region
PJM
Developer
—
Utility
PENELEC
Entity
PJM
Point of Interconnection
Jefferson 12.5 kV
Data Source
LBNL + Live
No news available for this project.