— Project Summary

Queue ID
PJM-AH2-065
Capacity
1.992 MW
Technology
Solar
Status
active
Location
Prince George's, MD
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL + Live

1.992 MW generation in Prince George's, MD · In queue since December 2021 · Proposed COD December 2022

1.992 MW

Capacity

1

Components

Solar

4y 3m

In Queue

In Progress (unknown study)

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

1 year

Schedule

40 months past proposed COD

In Study38%
Queue EntryDec 31, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-12-01

Project Details

State

MD

County

Prince George's

Region

PJM

Developer

Utility

DPL

Entity

PJM

Point of Interconnection

TBD 69kV

Data Source

LBNL + Live

No news available for this project.