BetaActiveSolarPJMLBNL + Live
5 MW generation in Chester, PA · In queue since December 2021 · Proposed COD May 2023
5 MW
Capacity
1
Components
Solar
4y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
1y 5m
Schedule
35 months past proposed COD
In Study38%
Queue EntryDec 31, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-05-01
Project Details
State
PA
County
Chester
Region
PJM
Developer
—
Utility
PECO
Entity
PJM
Point of Interconnection
TBD 34kV
Data Source
LBNL + Live
No news available for this project.