BetaActiveSolarPJMLBNL + Live
29.9 MW generation in Buckingham, VA · In queue since December 2021 · Proposed COD December 2025
29.9 MW
Capacity
1
Components
Solar
4y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
4 years
Schedule
4 months past proposed COD
In Study38%
Queue EntryDec 23, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-01
Project Details
State
VA
County
Buckingham
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Scottsville - CVEC Delivery Point 46 kV
Data Source
LBNL + Live
No news available for this project.