1.98 MW generation in Wicomico, MD · In queue since December 2021 · Proposed COD December 2022
1.98 MW
Capacity
1
Components
Solar
4y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
1 year
Schedule
40 months past proposed COD
In Study38%
Queue EntryDec 21, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-12-02
Project Details
State
MD
County
Wicomico
Region
PJM
Developer
—
Utility
DPL
Entity
PJM
Point of Interconnection
Edgewood 12.47 kV I
Data Source
LBNL + Live