BetaActiveBatteryPJMLBNL + Live
20 MW storage in Accomack, VA · In queue since December 2021 · Proposed COD June 2025
20 MW
Capacity
1
Components
Battery
4y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 6m
Schedule
10 months past proposed COD
In Study38%
Queue EntryDec 19, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-06-02
Project Details
State
VA
County
Accomack
Region
PJM
Developer
—
Utility
ODEC
Entity
PJM
Point of Interconnection
Tasley 69kV
Data Source
LBNL + Live
No news available for this project.