BetaActiveSolarPJMLBNL + Live
20 MW generation in Mecklenburg, VA · In queue since December 2021 · Proposed COD December 2025
20 MW
Capacity
1
Components
Solar
4y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
4 years
Schedule
3 months past proposed COD
In Study38%
Queue EntryDec 16, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-15
Project Details
State
VA
County
Mecklenburg
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Kerr Dam - Buggs Island 115kV
Data Source
LBNL + Live
No news available for this project.