— Project Summary

Queue ID
PJM-AH2-040
Capacity
11.5 MW
Technology
Solar
Status
active
Location
Tucker, WV
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL + Live

11.5 MW generation in Tucker, WV · In queue since November 2021 · Proposed COD December 2024

11.5 MW

Capacity

1

Components

Solar

4y 4m

In Queue

In Progress (unknown study)

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3y 1m

Schedule

15 months past proposed COD

In Study38%
Queue EntryNov 13, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-12-31

Project Details

State

WV

County

Tucker

Region

PJM

Developer

Utility

APS

Entity

PJM

Point of Interconnection

William - Blackwater 69 kV

Data Source

LBNL + Live

No news available for this project.