BetaActiveBatteryPJMLBNL + Live
60 MW storage in Prince William, VA · In queue since November 2021 · Proposed COD December 2026
60 MW
Capacity
1
Components
Battery
4y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
5y 1m
In Study38%
Queue EntryNov 9, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-31
Project Details
State
VA
County
Prince William
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Possum Point 115kV
Data Source
LBNL + Live
No news available for this project.