— Project Summary

Queue ID
PJM-AH2-028A
Capacity
20 MW
Technology
Solar
Status
active
Location
Pickaway, OH
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL + Live

20 MW generation in Pickaway, OH · In queue since November 2021 · Proposed COD October 2025

20 MW

Capacity

1

Components

Solar

4y 4m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 11m

Schedule

5 months past proposed COD

In Study38%
Queue EntryNov 2, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-10-28

Project Details

State

OH

County

Pickaway

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Watertower - Kingston 69 kV

Data Source

LBNL + Live

No news available for this project.