BetaActiveSolarBatteryPJMLBNL + Live
200 MW hybrid in Fountain, IN · In queue since October 2021 · Proposed COD June 2027
200 MW
Capacity
1
Components
Solar
4y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5y 8m
In Study38%
Queue EntryOct 29, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-06-01
Project Details
State
IN
County
Fountain
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Eugene - Dequine 345 kV
Data Source
LBNL + Live
No news available for this project.