BetaActiveSolarBatteryPJMLBNL + Live
150 MW hybrid in Barren, KY · In queue since October 2021 · Proposed COD November 2026
150 MW
Capacity
1
Components
Solar
4y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
5y 1m
In Study38%
Queue EntryOct 27, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-11-13
Project Details
State
KY
County
Barren
Region
PJM
Developer
—
Utility
EKPC
Entity
PJM
Point of Interconnection
Summer Shade - Barren County 161 kV
Data Source
LBNL + Live
No news available for this project.