— Project Summary

Queue ID
PJM-AH2-015
Capacity
110 MW
Technology
Battery
Status
active
Location
Lee, IL
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryPJMLBNL + Live

110 MW storage in Lee, IL · In queue since October 2021 · Proposed COD March 2025

110 MW

Capacity

1

Components

Battery

4y 5m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 5m

Schedule

12 months past proposed COD

In Study38%
Queue EntryOct 20, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-03-24

Project Details

State

IL

County

Lee

Region

PJM

Developer

Utility

ComEd

Entity

PJM

Point of Interconnection

Nelson 138 kV

Data Source

LBNL + Live

No news available for this project.