BetaActiveSolarPJMLBNL + Live
40 MW generation in Morrow, OH · In queue since October 2021 · Proposed COD December 2024
40 MW
Capacity
1
Components
Solar
4y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 2m
Schedule
15 months past proposed COD
In Study38%
Queue EntryOct 8, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-12-31
Project Details
State
OH
County
Morrow
Region
PJM
Developer
—
Utility
ATSI
Entity
PJM
Point of Interconnection
Galion 138 kV V
Data Source
LBNL + Live
No news available for this project.