BetaActiveOtherPJMLBNL + Live
10.12 MW generation in Fayette, OH · In queue since October 2021 · Proposed COD June 2024
10.12 MW
Capacity
1
Components
Other
4y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 8m
Schedule
22 months past proposed COD
In Study38%
Queue EntryOct 4, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-06-01
Project Details
State
OH
County
Fayette
Region
PJM
Developer
—
Utility
Dayton
Entity
PJM
Point of Interconnection
Texas Eastern - Jeffersonville 69 kV
Data Source
LBNL + Live
No news available for this project.