— Project Summary

Queue ID
PJM-AH2-002
Capacity
80 MW
Technology
Solar
Status
active
Location
Barren, KY
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL + Live

80 MW generation in Barren, KY · In queue since October 2021 · Proposed COD December 2024

80 MW

Capacity

1

Components

Solar

4y 5m

In Queue

In Progress (unknown study)

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3y 2m

Schedule

15 months past proposed COD

In Study38%
Queue EntryOct 2, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-12-31

Project Details

State

KY

County

Barren

Region

PJM

Developer

Utility

EKPC

Entity

PJM

Point of Interconnection

Temple Hill - Roseville 69 kV

Data Source

LBNL + Live

No news available for this project.