3.6 MW generation in Susquehanna, PA · In queue since October 2021 · Proposed COD December 2023
3.6 MW
Capacity
1
Components
Other
4y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
2y 2m
Schedule
27 months past proposed COD
In Study38%
Queue EntryOct 1, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-12-31
Project Details
State
PA
County
Susquehanna
Region
PJM
Developer
—
Utility
PENELEC
Entity
PJM
Point of Interconnection
Rattlesnake Hill Waste Heat Recovery