South Bend 500 kV — Project Summary

Queue ID
PJM-AH1-734 - moved to TC2
Capacity
1058.4 MW
Technology
Gas
Status
active
Location
Indiana, PA
Region
PJM
Developer
IA Status

South Bend 500 kV

BetaActiveNatural GasPJMLive · PJM

1,058.4 MW generation in Indiana, PA · In queue since April 2025

1,058.4 MW

Capacity

0

Components

11 months

In Queue

IA Status

Interconnection Timeline

Total Duration

11 months

Pre-Study0%
Queue EntryApr 10, 2025

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

PA

County

Indiana

Region

PJM

Developer

Utility

APS

Entity

PJM

Data Source

Live · PJM

No news available for this project.