Linden 230kV
BetaActiveNatural GasPJMLive · PJM
806.4 MW generation in Union, NJ · In queue since April 2025
806.4 MW
Capacity
0
Components
11 months
In Queue
—
IA Status
Interconnection Timeline
Total Duration
11 months
Pre-Study0%
Queue EntryApr 8, 2025
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
NJ
County
Union
Region
PJM
Developer
—
Utility
PSEG
Entity
PJM
Data Source
Live · PJM
No news available for this project.