— Project Summary

Queue ID
PJM-AH1-644
Capacity
100 MW
Technology
Solar
Status
active
Location
KY
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL

100 MW generation in KY · In queue since September 2021 · Proposed COD January 2026

100 MW

Capacity

1

Components

Solar

4y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4y 4m

Schedule

3 months past proposed COD

In Study38%
Queue EntrySep 15, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-01-01

Project Details

State

KY

County

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Spicewood 138 kV

Data Source

LBNL